A cable laying of 220 kV system renovation project of Liuzhou Power Plant commenced

A cable laying of 220 kV system renovation project of Liuzhou Power Plant commenced At 9:30 on the morning of December 14, the cable laying work for the 220 kV system renovation project of the Liujiaxia Hydropower Plant was fully carried out.

The cable laying work is a series of work for the transformation of the 220 kV system at Liujiaxia Hydropower Plant. Due to the high degree of difficulty, high intensity and tight schedule, Liu Power Plant urgently mobilized 100 people to fight once for laying cables. The Liugong Power Plant’s main attack unit staff consisted of more than 100 communists and young commandos supporting the front line.

Due to the limited on-site conditions, only a small amount of cables can be slowly moved by manpower. The joint efforts of the cadres and staff at the scene are close to the end. Before the completion of the work in the afternoon, the cable laying task was successfully completed.